PIERRE, (KCCR) — Dozens of residents, business owners and first responders took turns Thursday learning about the Euclid Avenue Reconstruction project. Morris Incorporated Operations Manager T-J Gallagher started with a baseline for the two year project…
Traffic will be maintained on Sioux Avenue and work on the S-Curve section will be done in segments to keep business access available…
Access to the Federal Building will be maintained during the early weeks of the project…
The 300 block of Pierre Street will become a two-way one-way road with a cul-de-sack on the north end. Parking will be reversed and traffic will enter and exit from Dakota Avenue. Work also includes a major storm drain improvement that will require pedestrian detours in Hilger’s Gulch. The project begins March 31st.
Comments