PIERRE — The Pierre City Commission has approved the first change order on the outdoor municipal pool project. Project Manager Gidget Palmer says some issues were found during construction of the pool….
Some changes for electrical conduit were made to meet code issues for some variable speed pumps. The change order also includes over 14-thousand 600 dollars in changes to the flumes to bring sunlight in…
Also included is nearly 25-thousand dollars for finish work on a concrete retaining wall that will include stain and an anti-graffiti coating. Commissioner Todd Johnson questioned Palmer about the charges in the change order…
The Commission approved the change order on a four-to-one vote with Commissioner Todd Johnson voting against the request.